Installing Electrical Power for Two 3.5kW Chili Pepper Dryers


This field project involved upgrading an existing agricultural electrical system to supply two 3.5kW electric chili pepper dryers at a farm in Icheon, South Korea.

The dryers had not yet arrived at the site. Before the work began, I spoke with the dryer supplier by phone and was told that each unit had a power consumption of approximately 3.5kW at single-phase 220V.

The installation itself was not especially complicated. The more interesting part was deciding how much of the existing electrical system could reasonably be used, selecting the branch protection, and later discovering that the actual dryer layout was different from the drawing provided before construction.

Project Overview

Location: Icheon, South Korea
Supply: Single-phase 220V
Existing contracted power: 5kW
New equipment: Two 3.5kW chili pepper dryers + small ventilation fan
Existing main breaker: 2P 30A ELCB
Upgraded main breaker: 2P 40A MCCB
Dryer branch protection: 2P 20A ELCB per dryer circuit
Dryer feeder: CV 3C 2.5mm² × 2 circuits
Actual cable run: Approximately 35m per circuit
Chili pepper farm and utility pole before electrical installation for two 3.5kW dryers

Overall view of the chili pepper farm before electrical work began.

Existing Agricultural Electrical System

Before modifying the panel, I inspected the existing agricultural electrical supply.

The service cable coming down from the utility pole was CV 2C 6mm². From the utility meter to the line side of the main breaker, 6mm² HIV conductors were installed.

The installed utility meter was rated 50(10)A.

The existing panel included:

  • 2P 30A Earth Leakage Circuit Breaker as the main breaker
  • One 2P 20A branch Earth Leakage Circuit Breaker
  • A power factor correction capacitor
  • An existing receptacle circuit

The site's existing contracted power was 5kW.

Existing agricultural distribution panel with 2P 30A main ELCB and 2P 20A branch ELCB before the electrical upgrade

Existing agricultural distribution panel before modification.

Why I Chose 20A Branch Breakers

One of the main decisions on this job concerned the breaker sizes for the two dryers.

The dryer supplier told me by phone that they wanted a 30A Earth Leakage Circuit Breaker for each dryer.

However, the machines were not yet at the farm, so I could not inspect their nameplates or verify the manufacturer's rated current directly. The information available to me was that each dryer consumed approximately 3.5kW at 220V.

Technical Note

Using the information available at the time:
3,500W ÷ 220V ≈ 15.9A
This is a simplified current estimate based only on power and voltage. It is not a verified manufacturer nameplate current.

From the information I had about the equipment, the dryer was primarily an electric heating appliance with only a relatively small fan motor. I therefore did not expect the type of large starting current associated with a substantial motor load.

Based on the expected operating characteristics and the information available at the time, I selected a 2P 20A ELCB for each dryer branch circuit.

This was a field judgment for this particular installation. It should not be interpreted as a general rule that every 3.5kW dryer should use a 20A breaker.

Important: For a new installation, the actual equipment nameplate, manufacturer requirements, conductor installation conditions, applicable electrical regulations, and load characteristics should be confirmed before final breaker and conductor selection.

Upgrading the Main Distribution Panel

The original main breaker was a 2P 30A ELCB.

With two dryers rated at 3.5kW each, the connected dryer load alone was approximately 7kW, with only a relatively small amount of additional load expected at the site.

I replaced the existing 30A main breaker with a 2P 40A MCCB.

At single-phase 220V, 40A corresponds to a theoretical apparent-power limit of:

220V × 40A = 8.8kVA

The existing service conductors, the 50(10)A utility meter, expected load pattern, and the site's 5kW contracted power were all considered when reviewing the existing supply.

A substantially larger electrical service would have required a broader review of both the installation and the utility supply conditions.

To make room for the additional branch breakers, I also removed the existing power factor correction capacitor from the enclosure.

The upgraded panel included:

  • 2P 40A MCCB as the main breaker
  • Additional 2P 20A Earth Leakage Circuit Breakers
  • 30mA leakage sensitivity on the installed branch ELCBs
Upgraded agricultural distribution panel with 2P 40A MCCB and three 2P 20A ELCBs for the well pump and two dryer feeder circuits

Agricultural distribution panel after upgrading the main breaker to 40A and adding dedicated 20A branch circuits.

Installing Two Feeder Circuits

Before I arrived at the farm, the customer had measured the route and told me that approximately 40m of cable would be required for each dryer circuit.

Based on that information, I prepared two runs of CV 3C 2.5mm² cable.

After completing the actual installation, approximately 5–6m remained from each 40m length. The real cable route was therefore closer to 35m per circuit.

Each three-core cable was used for line, neutral, and protective earth, with one conductor serving as the protective earth conductor.

The basic installation sequence was:

  1. Confirm the planned cable route
  2. Install CD conduit where required
  3. Insert fish tape through the conduit
  4. Pull the CV 3C 2.5mm² cables
  5. Terminate the circuits at the new enclosure
Pulling CV feeder cables through CD conduit across a chili pepper farm using fish tape

Installing the feeder route across the farm and pulling the CV cables through the conduit using fish tape.

The Equipment Layout Was Different From the Drawing

This became the most useful lesson from the project.

Before construction, the customer provided a drawing showing the two dryers installed in separate locations. The customer also told me by phone that he had measured the cable route and that two 40m runs would be sufficient.

Based on that information, I prepared and began installing two independent feeder circuits.

After the wiring work had already begun, I learned that the two dryers would actually be installed side by side.

What I Would Do Differently Today

If I had known the final equipment layout from the beginning, I would have considered:
Existing Panel

One 6mm² Feeder

Local Distribution Panel Near the Dryers

40A Main Breaker

Separate 20A Branch Circuits
With both dryers located side by side, this arrangement would have provided a cleaner local distribution point and avoided running two long 2.5mm² feeder circuits along essentially the same route.

Existing, As-Built, and Alternative Design

The diagram below compares three different configurations.

  • Existing System: The agricultural electrical system before the upgrade.
  • As Built: The configuration actually installed during this project.
  • Alternative Design: The arrangement I would have considered if the final dryer locations had been known before the wiring began.

The alternative design shown here was not the system installed at this site. It is included to explain how accurate equipment-location information can change feeder and distribution planning.

Electrical one-line diagram comparing the existing system, as-built installation, and alternative 3C 6mm² feeder design for two 3.5kW chili pepper dryers

Comparison of the existing electrical system, the actual installation, and an alternative local distribution design.

Weatherproof Distribution Box at the Dryer Location

At the dryer location, I installed a 300 × 200 weatherproof enclosure for the final circuit connections.

The two dryer feeder circuits were brought into this enclosure. A small window-type ventilation fan was also supplied from one of the dryer circuits.

The ventilation fan was a very small load compared with the dryer. Because I did not record its exact nameplate rating, I am not assigning a specific wattage to it here.

Installing and completing the wiring inside a weatherproof distribution panel for two chili pepper dryer circuits

Installing and completing the wiring inside the weatherproof distribution panel at the dryer location.

Temporary Cable Routing for Seasonal Use

There was another site-specific condition that affected the work.

The farm layout would change after the chili pepper growing season, and the customer planned to remove the cables after harvest.

For a permanent outdoor installation, I would normally prefer a properly protected permanent cable-routing method rather than leaving feeder cables exposed at ground level.

In this case, however, the customer specifically requested a temporary seasonal arrangement that could later be removed.

Temporary electrical feeder cable routed across a chili pepper field for seasonal dryer operation

Temporary feeder cable routing across the field for seasonal use.

Working Against the Weather

The work was carried out in midsummer. The temperature was above 30°C (86°F), humidity was high, and heavy rain was forecast for later in the afternoon.

We started at approximately 9:30 AM and completed the work at around 3:00 PM.

The site was approximately 80km from my home, requiring roughly 2.5 hours of driving each way. With rain approaching, efficient preparation was particularly important that day.

Completed electrical installation with feeder cables and local distribution panel at the chili pepper dryer location

Completed electrical installation at the dryer location before the two dryers were delivered.

Tools and Materials Used

The main tools and materials used during the installation included:

  • Battery-powered hydraulic crimping tool
  • Fish tape
  • Cable cutter and wire stripper
  • Multimeter
  • 2P 40A MCCB
  • 2P 20A Earth Leakage Circuit Breakers
  • CV 3C 2.5mm² cable
  • CD conduit
  • Cable lugs and connectors
  • 300 × 200 weatherproof enclosure

The battery-powered hydraulic crimper was particularly useful because it allowed cable terminations to be completed quickly and consistently while we were working against the approaching rain.

Klauke battery-powered hydraulic crimping tool, CV cables and electrical materials prepared for the dryer power installation

Electrical tools, CV cables and connection materials prepared on site before installation.

Final Result and Field Lesson

By the end of the work, the electrical infrastructure was ready for the two 3.5kW dryers, although the machines themselves had not yet arrived at the farm.

Looking back, the most valuable part of this project was not the physical installation itself.

The two independent feeder circuits were installed according to the equipment-location information available when the job began. Once I learned that the dryers would actually be placed side by side, it became clear that a different distribution arrangement could have been cleaner.

If I were planning the same installation again with the final layout known in advance, I would consider bringing one larger feeder to a local distribution panel beside the dryers and branching the individual circuits there.

Field Lesson

On a small electrical project, equipment location can affect the wiring design almost as much as equipment capacity. Confirming the final equipment position before preparing long feeder runs can reduce unnecessary cable and produce a cleaner distribution layout.

Electric Korea
Korean Electrical Construction · Field Experience · Safety · Technical Education
Website: electrickorea.co.kr